Here's the schedule for the renovation work being done on the
Kenworthy. If anyone would like to come and help, just show up on the day
and times listed. We need help with this project and hope to see you
there!!
Preliminary Construction Schedule / KPAC Construction
Fall 2000
Monday 9/4 9:00 - 3:00
Demolition New Dimmer Room, Prop Screen, Dimmer
Move, 'Front Entrance' Demolition
Sunday 9/10 10:00 - 4:00
Dimmers Install/Wire, Proscenium Restoration
Sunday 9/17 10:00 - 4:00
Stage Construction I
Sunday 9/24 10:00 - 4:00
Stage: Construction II
Sunday 10/1 10:00 - 4:00
Stage: Masonite Cover & Paint
Saturday 10/14 10:00 - 4:00
Battens & Rigging (Screen and On Stage)
Sunday 10/15 10:00 - 4:00
Notes & Punch List, Paint Proscenium
Sunday 10/29 10:00 - 4:00
Hang Softgoods
As you can see we have a lot of work to do in a short time, and many hands
make light work. If you have any questions call Jerry 882-1223/882-8915 or
Dean 885-6465
Thanks,
Jerry Schutz