Bike Path Project Update:
Most of the project elements on 6th Street are complete. Work is
progressing according to schedule on the abutments for the new
bridge.
All of the curb cuts and concrete details were poured today. Structural
fill is being placed and compacted today and tomorrow. The contractor
hopes to pave the majority of the path this Thursday.
The path will not be opened for use immediately following the
paving, however. Obviously, there is no bridge spanning Paradise Creek
yet. In addition, the exposed gravel shoulders must be protected with
topsoil before they are exposed to bike traffic.
The project is generally ahead of schedule, and it should only be a matter
of a few more weeks until it is complete.
Ron Force rforce@belle.lib.uidaho.edu